Solution Brief – Acuren Partners with An Energy Leader to Provide Access Solutions
Acuren partnered with an energy company to support their TA/Maintenance program. Acuren’s access planner worked with the client’s planning and execution team to review any work scopes that could be executed via rope access instead of scaffolding to reduce the overall time and cost.
Underside of Bridge Emergency Water Main Repair
There are two 30 inch diameter ¼” wall thickness steel water mains, which run along the underside of the bridge over a river way, that provide major water distribution to the community. The leak locations were difficult to access and on pipe which had an old asbestos coating. Acuren’s engineering and rope access crew provided a safe, economical, and timely repair solution to get the lines back into operating condition.
Flare Stack – Extending Operating Life of Critical Legacy Asset
This oil and gas customer had a 60 year old flare stack with cracking and corrosion that was approaching its end of life. Due to the cracking and corrosion thinning, there was considerable potential for failure for the flare tip and stack pipe. The cost for flare stack replacement was significant and Acuren offered a solution for life extension rather than stack replacement.
Integrated Solutions
Acuren integrated solutions are saving our clients time and money. Acuren safely completed a flare tip replacement and coatings project in Ohio at a fraction of the time and at 40% of the cost. The four-week project incorporated Acuren’s Mechanical, Engineering, and Rope Access Industrial Services.
Rope Access Turns “No Way” Into Project Success
8 day window for the replacement of 2 wear plates in coke chutes for an Athabasca Oil Sands client just north of Fort McMurray.
Ropes Team Saves Thousands on Pump Box Work